/NEWS

The new trigeneration plant in the Mezzani factory is in operation

13-02-2020
Category: COMPANY

Fepa  - Articolo - Impianto di trigenerazione

A 1.2 MW trigeneration plant went into operation at the Casale di Mezzani factory. The plant was built using all the best available technologies and is one of the rare cases of an “ISLAND” plant interconnected to the plant’s equipment. Together with the 1 MW photovoltaic plant already present since 2012, the tri-generator makes the production site self-sufficient and highly sustainable.

This choice confirms our commitment to systematically reducing our environmental impact by adopting more efficient and green solutions.